EON - Citigen Design and build: Installation of water cooled chillers

company name here

Client : EON, Citigen

Value: £660,000.00

Project: Design and build: Installation of water cooled chillers

 

Time scale

4 months

This project was to replace the existing water cooled chillers and add additional cooling to the centralised district cooling system.

We installed HV/LV substation and switchgear, three new water cooled chillers, pumps and the associated Pipework.

 

Energy Efficiency

The...

find out more

BGP- Bicester New Print Factory Extension

company name here

Client : BGP – Bicester

Value: £1,100,000.00

Project: Design and build: Installation of mechanical services, temperature control and temperature control to new factory

 

Time scale

12 months

 

Scope

This project involved designing and installing the following, to support 3 x MAN printing presses:

3 x Air cooled chillers 800kW

2 x Dry air coolers

Circulating pumps

2 x Temperature control...

find out more

Westfield Shopping Towns The Eagle Centre - Derby

company name here

Client : Carrier / Westfield

Value: £400,000.00

Project: Design and build: Installation of mechanical services to chillers and Air Handling units


Time scale

12 months

 

Scope

This project involved designing and installing the mechanical services from the Carrier air cooled chillers to the air handling plant.

find out more